Planning a lithography workstation

Spin coating, baking and developing release solvent vapour and handle hazardous chemicals, so they belong in an enclosure with controlled airflow. Whether it’s a single benchtop coater or a full coat, bake and develop line, a little planning before the order goes in saves expensive changes later. This guide covers what to settle with your facilities and safety teams.

Ducted or recirculating

  • Ducted workstations connect to the building exhaust and take vapour out of the room. They suit any solvent load and are the safer default for lithography.
  • Recirculating (ductless) enclosures filter the air and return it to the room. They avoid ductwork, but filters must be changed before they saturate, and they aren’t suitable for highly toxic materials, large volumes of solvent, or gases such as carbon monoxide and hydrogen.

Many workstations use a fan filter unit to supply clean, filtered downflow over the work surface, with the exhaust drawing air out through the deck and the process bowls.

Airflow

  • Face velocity. UK practice for fume cupboards is commonly at least 0.5 m/s across the working opening. Wet benches in fabs are often specified at around 100 feet per minute or more.
  • Capture at the source. Exhaust from each spin bowl and bake plate hood takes vapour away where it’s made. Heated processes need more capture than unheated ones.
  • Balance. The total exhaust needs to exceed the filtered downflow slightly, so the enclosure stays under negative pressure and vapour can’t escape into the room.

Ask the supplier for the exhaust flow and static pressure the workstation needs, and check the building system can deliver it before the tool arrives.

Yellow light

Photoresists are sensitive to blue and ultraviolet light. Yellow lighting, which blocks wavelengths below about 500 nm, protects them during coating and handling. Light from windows and nearby rooms needs filtering too.

Containment and storage

  • Spill containment under liquids should hold at least 110% of the largest container.
  • Chemical storage in exhausted cabinets or drawers keeps solvent bottles close to the process without vapour reaching the room.
  • Waste needs a clear route, with solvent and aqueous waste kept apart where the chemistry requires it.

Utilities

List everything the tools in the workstation need, and add a margin for future modules:

  • mains power and the number of outlets
  • vacuum, from house supply or dedicated pumps
  • nitrogen and clean dry air, with pressures
  • DI water and drains, if a developer is included
  • exhaust connections and flow

LEV testing

In the UK, local exhaust ventilation is covered by COSHH. A workstation used to control exposure to hazardous substances needs a thorough examination and test at least every 14 months, following HSE guidance HSG258, with records kept for at least five years. Keep the commissioning airflow figures from installation, because they’re the baseline for every later test.

Safety marks and documents

Check the workstation arrives CE marked, with a declaration of conformity and instructions, and ask for any reports your site needs, such as SEMI S2 assessments. Our guide to CE, UKCA and NRTL explains what each mark covers.

How SiSTEM can help

The CEE X-Pro II workstation comes in half and full sizes, ducted or with a fan filter unit, and holds Apogee spin coaters, bake plates and developers under one exhaust enclosure. It’s CE marked, with a full-face sash, yellow lighting and exhausted storage. Our X-Pro II options page covers the tops and accessories. Send us your room layout, utilities and process list, and we’ll plan the workstation with CEE.